Dinh Vu – Cat Hai Economic Zone, with the core being Nam Dinh Vu Industrial Park, has been affirming its position as one of the key industrial and logistics centers of the North. This development has led to a great demand for modern factory infrastructure, especially the highly flexible ready-built factory for rent model.
Grasping that need, Hai Long Steel Structure is currently implementing the steel structure construction project for the project "Factory for rent and auxiliary items" of the investor, Dumei Vietnam Co., Ltd. The project is a testament to Hai Long's capacity in providing effective construction solutions, meeting strict standards on progress and quality.
Project overview information
- Project: Factory for rent and auxiliary items Dumei Vietnam
- Where to eat: Lot CN 5.1B, Nam Dinh Vu Industrial Park, Hai Phong
- Scope of work: Steel structure construction
- Mass: More than 1.200 tons
- Progress target: 70 days
To meet this schedule, our workflow is organized as follows:
- At the factory: Production lines operate continuously to process components according to plan. Quality control at the source ensures that products leaving the factory meet the highest technical standards.
- At the construction site: The installation team and equipment are properly arranged, ready to receive and begin assembly as soon as the components are transported.
The smooth coordination between these two locations is the key factor that helps us control and speed up the overall progress of the project, while ensuring quality and safety throughout the construction process.