Update progress of GNP Nam Dinh Vu project on 04/05/2023. The project with a total value of more than 700 billion, has an area of 170.000m2 total including a warehouse, 6 factories and an operator. The project will be completed in July 07.
The factories in the construction phase are as follows:
Factory No. 2 has an area of 2 hectares, currently constructing reinforcement ready for pouring concrete.
Factory No. 3 is currently leveling the base stone layer for the foundation, steel structure, purlins and roof have been completed to prepare for corrugated iron roof, safety nets are always stretched to ensure the safety of roofing workers. .
Factory No. 4 is compacted, has basically completed the foundation and has been roofed with corrugated iron, the concrete floor is covered with a sealed nylon layer to keep moisture in, helping the concrete layer to reach the best quality.
The team of engineers as well as workers are trying non-stop every day, every hour to complete the factory areas, in order to ensure the schedule that Hai Long Construction Contractor has committed to the investor as well. to ensure the quality of the project.