Hai Long Construction Contractor excellently completed the project of Jinka material technology factory phase 1 and phase 2. Continuing to gain the trust and selection from the investor, Hai Long Construction started to work. Construction phase 3 and will be completed in August 08. The project with a total investment value of more than 2023 billion VND with a construction area of 300m35.000.


Phase 3 of the project includes 6 items, including 3 main workshops, raw material warehouse, garbage mill and fire protection system. Each item is entering the construction phase as follows:
- Workshop 3 and Workshop 4 are located in the middle of the Project, which has completed the construction of concrete, reinforcement, foundation and columns of the 1st floor; The second floor is finishing concrete, reinforcement, beams and floors at 2%.
- Workshop 5 is located behind workshop 3 and workshop 4, basically finished concrete, reinforcement, foundation and columns on the 1st floor; concrete, reinforcement, floor beams on the 2nd floor reached 80%.
- The raw material warehouse has completed the hard frame, concrete, reinforcement, beams, 2nd floor floor, preparing the steel structure and constructing the roof cover.
- Garbage house has completed concrete, foundation, wall covering structure, steel structure, preparing to gather materials for roofing construction.
- The water tank and fire protection area has been completed, ready for the installation of pumping equipment according to the project schedule.


Jinka Material Technology Factory Project is one of the important projects, affirming the position and prestige of Hai Long Construction and Construction with investors. The project is the enthusiasm, effort, and unrelenting efforts of Hai Long Construction Contractor together with a team of engineers and workers to ensure high quality works, focusing on safety and security. and achieve the progress as committed with the investor.