HAI LONG

Project HONGYUAN

Project HONGYUAN

Since the success of HongYuan 1 project in 2009, Hai Long contractor continues to be selected as the main contractor in the design of HongYuan 2,3 project in Do Son Industrial Park in Hai Phong. The evidence for that success is even more evident when Hai Long continues to be selected as the General Contractor for the design and construction of HongYuan 4's factory project also in Do Son Industrial Park, Hai Phong.

Hong Yuan factory project 4.

Investor: China- Location: L4.6, L4.7, L4.8A, Do Son Industrial Park, Hai Phong.

Industry: Manufacturing, processing, assembling mechanical products, manufacturing steel plate with a total land area of ​​30,000m2,

Factory area is 16,000m2, contract value is over 60 billion dong (2,7 million USD), construction time is 4 months.

Some pictures: