The People's Committee of Bac Ninh province has just issued Decision No. 330/QD-UBND approving the project to adjust the Zoning Plan. industrial area (Industrial Park) Que Vo expansion 2, scale 1/2.000.
Accordingly, the MN02 drainage canal was adjusted to move to the West, adjacent to the western boundary of the industrial park, adjacent to the residential area of Yen Gia village (Chi Lang commune). The adjustment helps ensure drainage for the entire area, while increasing the drainage capacity for the existing residential area. The drainage direction, connection points and technical solutions remain the same as the previously approved master plan, ensuring consistency in technical infrastructure.
Notably, Bac Ninh province also decided to merge land lots B and C into lot BC with an area of about 32,6 hectares; merge land lots E and F into lot EF with an area of 22,85 hectares. This merger aims to create large-scale land funds, suitable for arranging production lines, factories and auxiliary items according to the actual needs of investors. The above adjustments are only local, not changing the land use structure as well as the overall scale of the project.

Previously, in August 2025, the People's Committee of Bac Ninh province approved the 1/2.000 scale zoning plan of Que Vo Industrial Park 2 expansion, invested by Kinh Bac Urban Development Corporation - JSC (KBC). The industrial park has a total area of over 140,3 hectares, located in Bong Lai ward, Phuong Lieu ward and Chi Lang commune. Of which, about 91 hectares are planned to build factories and enterprises; more than 13 hectares are for administrative - service items; the remaining area is for green trees, internal traffic and water surface.
According to the plan, the industrial park is divided into seven large lots with a maximum construction density of 70%, the height of industrial buildings not exceeding 7 floors. The service area is allowed to be built up to 18 floors with a density of 50%. The parking lot is located in the South, close to DT.287 road, serving the logistics and travel needs of workers.
Kinh Bac plans to start construction of the project in the first quarter of 2026, complete it in the fourth quarter of 2029 and possibly start operating from the second quarter of 2028. The total investment capital is about 1.878 billion VND, of which construction costs account for more than 1.176 billion VND, compensation and site clearance costs are about 702 billion VND.
Currently, Kinh Bac has invested in three industrial parks in Bac Ninh, including Que Vo, Que Vo expansion and Nam Son - Hap Linh. The implementation of Que Vo expansion 2 industrial park marks the fourth industrial project of the enterprise in the locality, while consolidating Kinh Bac's position in the field of industrial infrastructure development.
According to the investor’s orientation, Que Vo Expansion 2 will become a multi-industry, high-tech industrial park, focusing on attracting businesses in the fields of electronics, electronic components, precision mechanics and supporting industries. The project is expected to continue the success of the two previous Que Vo industrial parks – which have filled 100% of commercial land with a total investment capital of more than 3 billion USD since its operation in 2003.
With reasonable planning adjustments, synchronous infrastructure and orientation to attract high-tech investment, Bac Ninh is continuing to affirm its role as one of the leading industrial centers in the North, making an important contribution to the economic development strategy of the Capital region and the key economic region of the North.
Source: Observer Electronic Newspaper