Detailed instructions on conditions and procedures for applying for a construction permit with a term of 2024. This article will fully present the eligibility criteria, application process and validity period of the construction permit. license. Make sure your construction project meets the necessary qualifications and has the proper permits to complete on time.
1. What is a limited-term construction permit?
A construction permit with a term is a construction permit issued for the construction of works and individual houses that can be used for a certain period of time according to the construction planning implementation plan.
In particular, construction permit is a legal document issued by a competent state agency to investors for new construction, repair, renovation, and relocation of works.
(Clause 17, 18, Article 3 of Construction Law 2014, amended in 2020)
2. Conditions for granting a construction permit for a limited period
* General conditions for granting a construction permit with a limited term:
– Belonging to an area with construction zoning planning, functional area construction zoning planning or detailed planning, detailed functional area construction planning that has been approved and announced by a competent state agency but it has not been implemented and there is no land recovery decision from a competent state agency;
– In accordance with the scale of the project prescribed by the Provincial People's Committee for each area and the duration of the project's existence according to the plan for implementing construction zoning planning and functional area construction zoning planning. or detailed planning, detailed planning for construction of functional areas approved by competent state agencies;
– In accordance with the land use purpose determined in the legal land documents of the applicant for a limited-term construction permit;
– When the term of existence of the project as stated in the construction permit expires and the competent state agency has a decision to recover the land, the investor commits to self-destructing the project, if not self-destructing. will be forced and bear all costs for demolition.
If past this deadline the construction planning has not been implemented, the investor may continue to use the project until the competent state agency has a decision to recover the land. Support during demolition is carried out in accordance with the provisions of land law.
* Conditions for granting a limited-term construction permit for construction projects:
+ Ensuring safety for construction and neighboring works and requirements on environmental protection, fire and explosion prevention and control; ensure the safety of technical infrastructure, protection corridors of irrigation works, dykes, energy, traffic, cultural heritage areas, historical and cultural relics; Ensure a safe distance from flammable, explosive, toxic works and important works related to national defense and security.
+ The construction design has been evaluated and approved according to the provisions of Article 82 of the Construction Law.
+ The application file for a construction permit is appropriate to each type of permit as prescribed in Articles 95, 96 and 97 of the Construction Law.
* Conditions for granting a limited-term construction permit for individual houses:
– Ensuring safety for the project and neighboring structures and requirements for environmental protection, fire and explosion prevention and control; ensure the safety of technical infrastructure, protection corridors of irrigation works, dykes, energy, traffic, cultural heritage areas, historical and cultural relics; ensure a safe distance from flammable, explosive, toxic works and important works related to national defense and security;
– Individual house construction design is carried out according to the provisions of Clause 7, Article 79 of the Construction Law;
– Dossier to request a construction permit as prescribed in Clause 1, Article 95, Article 96 and Article 97 of the Construction Law.