On the construction site HHD Thai Ha project, the construction atmosphere is always exciting and urgent. Each item records important progress, reflecting the sense of responsibility, professionalism and determination of the entire Hai Long Construction general contractor team.
- Factory The 3-storey reinforced concrete frame has been completed. The plastering work has reached 60% of the volume, creating an increasingly clear appearance for this key area.
- Storehouse also recorded impressive construction speed when completing the reinforced concrete foundation, and installing steel structure, roofing and corrugated iron.
- Fire protection water tank and wastewater treatment tank All projects have been completed 100% of the volume, meeting safety and environmental standards.
- Auxiliary items Like the garbage house, the chemical warehouse has completed the hard frame, cover and roof, while guard house 1 and 2 are also completed and ready to be put into use.
- Garage The foundation has been completed and the base is being deployed, promising to be completed quickly to serve the needs of staff and workers.
- Special, MEP system (electrical, water supply and drainage, fire prevention and fighting...) are deployed in parallel with construction items, ensuring connectivity and optimizing operations for the entire project.
Looking back at the images at the HHD Thai Ha construction site, we can clearly see the efforts and smooth coordination of the Hai Long Construction team and related parties. This is not only a testament to the project's organizational and management capacity but also a strong commitment to quality, progress and safety of the general contractor.
Some pictures at the project site