General contractor project

GNP Nam Dinh Vu factory project

Investor:

Hong Kong

Package:

Construction general contractor

Project land area:

170,000 m2

Location:

Nam Dinh Vu, Dong Hai 2, Hai An, Hai Phong

map
Industrial center

GNP Dinh Vu

This is a project to build ready-built factories and warehouses in Nam Dinh Vu Non-Tariff and Industrial Zone, Hai An District, Hai Phong City with a construction land area of ​​up to 170.000m2. The project was built with the goal of providing a variety of ready-built factory and warehouse solutions with a minimum area of ​​2.500m2, meeting the increase in the supply chain. At the same time, ensuring strict standards on environmental protection and fire prevention; promises to bring Nam Dinh Vu Industrial Park another flexible infrastructure service, meeting the needs of small-scale investors.

100,000 m2

Construction area

07

Factory

01

Office building

Progressproject

  • Begin
    18/06/2022
  • Finish
    08/09/2023

Detailsproject

  • Complete & receive certificate from Investor

    Details
  • Entering the acceptance stage of Fire Prevention and Fighting

    Details
  • Project completion phase

    Details
  • Construction of factory 2,3,4

    Details
  • Establish 500.000 hours of labor safety. Handing over the first factory

    Details
  • Completed 41% of the project volume

     

     

    Details
  • Steel structure erection ceremony

  • Starting construction