Snow Coast Vietnam Factory Project is an important large-scale project, highly appreciated for its investment and technical requirements. Not only stopping at construction, Snow Coast also focuses on environmental protection. The project has set criteria to achieve LEED ZERO green certification, ensuring that the construction process does not have a negative impact on the surrounding environment.
After 6 months of construction, the project has progress reports on each item, specifically:
Factory category:
– Complete KCT erection and roofing.
– Base concrete pouring reaches 35%
– The work of installing glass walls, fire protection, and ME is underway.
=> Plan January 31, 01 will hand over the site to the Investor to install the machine
Office building category:
– Complete the hard frame and plastering.
– The work of installing glass walls, fire protection, and ME is underway
=> Plan January 31, 01 will hand over the site to the Investor to install machinery and equipment.
Categories of restaurants:
– Complete KCT and roofing.
– The work of installing glass walls, fire protection, and ME is underway
=> Plan January 31, 01 will hand over the site to the Investor to install machinery and equipment.
Warehouse category 4B:
– Complete KCT and roofing.
– The work of installing glass walls, fire protection, and ME is underway
=> Plan January 20, 01 will hand over the site to the Investor to gather equipment for the project.
Warehouse item 6B is an additional item but the basic progress will be met according to the total progress of the project:
– Complete KCT processing at the factory.
– Plan January 31, 1 to complete KCT erection and roofing.
Sub categories: Ensure according to the total progress and requirements of the Investor.
An overview of the project progress shows that the Hai Long Construction team is maintaining progress according to the investor's request. Construction quality is also strictly guaranteed, ensuring that the project will achieve high standards of quality and aesthetics.
Snow Coast Vietnam Factory is one of the projects that receives close attention from the Board of Directors and Investors. Being aware of that, right from the moment of "departing" we tried to concentrate as much as possible. Despite the urgent progress of the work and the continuous negative effects of the weather right from the beginning of construction, Hai Long Construction is still enthusiastic and determined to fight, towards the common goal that all brothers will continue to achieve. Continue to "burn" your best until you reach the finish line successfully!