With the persistent fighting spirit of the Board of Directors and workers at Jinka Project phase 3, the project is updated as follows:
- X3 workshop is erecting steel structure and roof purlin.
- Factory X4 has completed about 70% of the 2nd floor columns, preparing to erect the steel structure for the roof.
- X5 workshop completed about 90% of columns on the 2nd floor, preparing the ground for steel structure erection.
- X6 workshop has installed and erected the roof steel structure and roof purlins.
- X7 workshop has completed the construction of the roof covering structure.
Hai Long Construction always strives and tries, does not mind the harsh hot weather of summer to focus on the Project carefully and meticulously, ensuring security, safety and high quality to handover according to the schedule committed with the Investor.