Following the project of GNP Nam Dinh Vu industrial center which is in the finishing stage, Hai Long Construction Contractor continues to be selected by the Investor to complete the GNP Dong Van III project.
The project has a total land area: 16,04 hectares
Total building area: 96.150m2
The floor area of the building is 99.846m2
In which phase 1 total is 50.000m2 including X1, X2, X3 workshops and ancillary works.
GNP Dong Van III project is in construction phase I, specifically as follows:
- Factory X1, X2 and X3 have basically completed the foundation, 3 factories are building walls around the workshop and preparing to install steel structure.
- Ancillary items include garage; The fire protection area is under construction.
As one of the important projects, following the success of the GNP Nam Dinh Vu project, Hai Long Construction continues to affirm its position and prestige shown through the construction process of the GNP Dong Van III project. Hai Long Construction Contractor and a team of engineers and workers always strive day and night, ensuring security - safety during the construction process, ensuring the quality of the work and handing over on schedule as committed to the company. Investor.